Hi,
I want to create a filled that will automatically get the value of a date.
The date is the dat that the line got marked as done in the check box.
Possible?
10X
Will marking the task as "done" be the last action on the row? If so, you can use the Modified (Date) System column which shows a timestamp of when the row was last modified.
You can also view the history of any cell which include any change that was made, when the change was made, and who made the change by right clicking in the cell and selecting View History.