I am trying to write a formula that has multiple steps to it.
I want it to see if the project is completed then to give me the Max date of completion.
=MAX(COLLECT(B:B, C:C, "complete", A:A, "Act A"))
Are you trying to complete this in Smartsheet? If so, here is the Smartsheet version. It assumes your columns are titled the same as your headers in the excel example shown.
=MAX(COLLECT(Date:Date, Status:Status, "Complete",[Activity Type]:[Activity Type], "Act C"))
That works! Thank you. I am doing this in Smartsheet but I did my example in Excel.
Smartsheet Community - I AM STUMPED!! I am trying to do a crosssheet SUMIFS formula with 1 Column and 2 Rows of Data. I need to sum across {Weeks 1 to 104} Column to match : {Helper Column} = Baseline@row Vertical Rows {Month} needs to match Month@row, and Row {Year} needs to match Year@row I have tried SUMIFS, JOIN,…
Hello I am looking to create a Smartsheet formula that returns the following result: Column A "Created Date" - this column type is a Created date and show results with date and time Column B "Received Date" - this column would round up the "Created Date" and just show date, no time. If the "Created Date" was after 2:00pm…
Cant figure out why this is not working. It comes back NO MATCH. I have changed it to true and to 1. Nothing works. HELP