I'm trying to delete one task dependency on a Gantt chart. I found this quick YouTube video, which says to click the dependency line, but I'm unable to click on it. My dependency lines are not green like in the YouTube video. Thoughts?
Hello,
That YouTube video appears to be for a different piece of software other than Smartsheet.
If you're trying to delete a dependency in Smartsheet, delete the row reference that you see in the Predecessors column of the Grid portion of the sheet.
More information on dependencies in Smartsheet can be found in this help article: https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
We want to implement single-sign-on at work and have received approval. However, our IT department wants all external partners to have/use Mayo credentials to log into Smartsheet. Not all of our external partners ever set foot on our campus and don't have our company credentials. I have a couple of questions. Has any other…
I can create a Chart in Dashboard from sheet well but from Report is not working now. I just try with simple Report (just contain 2 column Primary and Number) but cannot make the chart. Is there any changes recently right, because I haven't worked with Smartsheet dashboard for a long time and I remembered that I could do…
Cant find this anywhere