Hi All,
I am trying to do a COUNTIF and refrence another sheet but I keep on getting an error.
=COUNTIF({Go New Products Range 1},Category:Category,"Footcare")
Hi jbusch30,
Here are the specifications for composing a countif formula.
https://help.smartsheet.com/function/countif
You'll want to make sure your Go New Products range is only selecting the "category" column from your sheet... If that is the case this should work for you.
=Countif({Go New Products Range 1}, "Footcare")
The formula will search through your range and return the count of each cell that has "Footcare" in it.
Hi,
can you tell me what is the problem with the syntax in this formula fror countif in another sheet.
=COUNTIF({project gantt - Superdry HPR area Range 1}, {project gantt - Superdry HPR area Range 2,"11"})
regards
Alan
Hi Alan, there are a couple of issues with the countif. It looks like you have two ranges when there should only be one... I'm not sure which range has the actual data you are trying to count, but try recreating it from scratch. If you are wanting to check if the data meets two different requirements you can use a =Countifs( ) formula and follow the requirements stated here: https://help.smartsheet.com/function/countifs
Hello, I'm working through the writing formulas optional activity and in the 'Nested IF function - Progress Column' task it directs you to put in the following formula '=IF([% Complete]@row = 0, “Empty”)'. However, when I put this formula into the spreadsheet, '04a_Marketing Request Tracker - Formulas', I get an…
I have an automation that has a condition where I am looking at the column "LEA Interco Supporting Site(s)" and trying to find columns that have the value "Fort Loramie" in them. This works well when "Fort Loramie" is the first item listed in the cell, but it doesn't work when "Fort Loramie" is the second or third value in…
Have any of you created a Smartsheet that would show the savings for a project by the month? In other words, if I saved $1200 annually and the project ended in say March, then the savings would go $120 per month, Mar 2025-Feb 2026. I have done it on Excel sheets manually, but I think there should be a way to do it with…