how do i build a formula that gives me the actual date for today + 35 working days?
=Workday(Today(), 39)
will give you 39 working days from today.
https://help.smartsheet.com/function/workday
You need to put that in a date column and you need to understand that the date will change each day you load the sheeet. Today() will always refresh with the current day's date.
Hope that helps!
awesome thanks
You're welcome!
Date Report Partner CBO Name 01/12/25 Children's org 05/15/25 Foodbank 08/30/25 Children's org 09/11/25 Chamber 11/25/25 Digital Bus 08/21/24 Digital Bus South 01/15/26 Children's org 01/12/24 Foodbank Sister 02/15/24 For the children org 07/01/26 Digital Bus #2 08/05/26 Family Center 12/01/26 Family Center I am trying to…
I am trying to get the passenger count per month per year, and I can't seem to get the formula correct. I need to add the number of passengers for each month per year. If anyone could assist me with this, I would greatly appreciate it. Thanks!
I need to edit a large sheet that has a lot of predecessors. I need to delete one row and move another. when I make the changes the predecessors for proceeding lines are not correctly displaying the dates correctly. Need help.