Sign in to join the conversation:
hello,
i am looking to find a way to do an average with the RYG balls.
ex: 2 green, 2 yellow, 2 red should have should show yellow ball for the overall project.
is this something possible?
thanks for your help
I can't help you with the method, but can I offer some thoughts?
When rolling up status (which isn't a great plan anyway), I always use the worse indicator rather than average.
e.g. if your project has 1 red indicator, it overrides 999 greens or yellows and I'd be reporting the overall status as red because you have an activity which isn't going to make it.
May be better to report on the number of reds, yellows and greens separately?
Not sure what metrics you are using or how you have defined RYG so happy to wind-my-neck-in if necessary!
I've got the following formula in a Check Box column to check when something is due in the Next 3 weeks. =IFERROR(IF(AND(WEEKNUMBER([Projected Cleaning Date]@row ) = WEEKNUMBER(TODAY()) + 3, YEAR([Projected Cleaning Date]@row ) = YEAR(TODAY())), 1), "") I have them for 2 weeks, 3 weeks, 4 weeks, and 5 weeks. These stopped…
I'm using salesforce connector to pull my team's hours information in real-time. The Salesforce connector sheet contains sheet summaries that I'd like to use a cell reference for a different sheet. I can't seem to find the best way or formula to do this. I don't want to use a dashboard with report widgets because I prefer…
I have two formulas which work well independently, but when I combine them they don't. formula 1: =IF(YEAR([Joined date]@row ) = 2025, JOIN(COLLECT({Membership Survey 2025 - Experience}, {Membership Prioritisation Survey 2025 - Org}, [Organisation name]@row ))) formula 2: =IF(YEAR([Joined date]@row ) < 2025,…