Sign in to join the conversation:
Hello All,
I am using this formula =TODAY() - [Date Field Checked]3 but I need to stop this count when the item is complete.
Could someone please help out?
How does the user signify complete? Check box, status text, or % Complete.
By stop the count, do you want it to return blank when complete or keep the last value?
Smartsheet does not do the second one -- I use Zapier for that if I have to. Or the API.
If just blank then
Assuming you have a checkbox in a column name Done
=IF(Done@row,"",TODAY() - [Date Field Checked]@row)
I hope this helps.
Craig
Hi Craig,
Thank you. I would like it to just store the value. They check "Partial- holding for rework" or "complete". As soon as complete is checked I just want it to hold.
Smartsheet won't do that.
It needs a toggle function or a set-reset function, which is does not have.
If this is a single sheet or a small fixed set of sheets, I would use Zapier.
What you are looking for an accumulator, not a counter. Now that I think about it, the API might be easier to implement such a thing.
I'm trying to create a formula that will output a Product category. Below is the formula and I've provided a screenshot of the columns involved. =IF(AND(Folder1 ="default", [Cost Category]1="Printer : Plex", ISNUMBER(FIND("Color",[Cost Option]1))), "Color Impressions", If(AND(Folder1="default", [Cost Category]1="Printer :…
Hi All, I have a project plan with a column called "Owner" that has a column type of contact list. The contacts are from multiple companies. It's a large project plan. I have created columns that have a column type of checkbox. I want to check the box if the owner is from a certain company (which can be determined by the…
I have an automated workflow set up to run weekly and request an update when the project is in certain statuses. The automation only ran once and now it's not working even though I have it set up to run weekly. I need help troubleshooting why this isn't working.