If you are familiar with MS Project, you are aware of the Reschedule Remaining Work functionality. Does this type of feature exist in Smartsheet? If not, what is used to "push" out work not completed to determine the new end date?
HI, nothing in the system will do that other than manual intervention to eg increase the duration to the delayed task/s or if it hasnt started at all to move the start date back. All manual I'm afraid.
Mick
Have any of you created a Smartsheet that would show the savings for a project by the month? In other words, if I saved $1200 annually and the project ended in say March, then the savings would go $120 per month, Mar 2025-Feb 2026. I have done it on Excel sheets manually, but I think there should be a way to do it with…
Hello team! Hope you all are having a wonderful holiday season. I am trying to set up an automation that will send an email reminder one time when Next Update Date = 60 days, then another automation at 30d, etc. The key is I only want it to send the reminder one time when Next Update threshold is reached. Is this possible?…
Has anyone found a workaround for sharing Smartsheet reports externally without giving access to internal data? I currently have to download the data and transfer it onto excel to create a pivot table for our client and I want to find an easier way to do so. I also already create a dashboard for our client, but I wanted…