Sign in to join the conversation:
Hello,
How do I get my % data to roll up to 100?
Its looking like all of the data is running up to 1.
Does that make sense?
Sorry for the hopefully easy questions.
Thanks
- Alex
Format the column to %
(4th from the right on the Format Bar)
I did this. Nothing changed.
You still see 0.36 instead of 36%?
The [% Complete] column treats 0-1 as 0-100%
Craig
That is correct.
I figured it out. I needed to select the % format.
D'OH!
Thanks,
Alex
Hey, I am using the below formula→ =INDEX({Source_Sheet_Entire_Table}, MATCH([Unique ID]@row , {Source_Sheet_ID_Column}, 0), 1) Although the answer should be "Project details" mentioned in Column 1, it says #No Match. What am I doing wrong?
How can I delete old sheets I no longer use from my account?
I'm trying to display a task progress chart showing "complete", "late", and "not complete" in my dashboard and for some reason the chart will display as a column chart but it won't display as a donut chart even though I'm referencing the same report. I'd prefer to display as a donut chart as I think it looks better and is…