Sign in to join the conversation:
Is there are way to track the amount of time each stage of development takes?
What formula would I use and then, what chart?
Hi Michelle,
Yes, there is. It depends on how your solution is setup. Can you share the solution or upload some screenshots?
I hope this helps you!
Best,
Andrée Starå - Workflow Consultant @ Get Done
Keep in mind... Tracking time in Smartsheet only works for days. Smartsheet cannot handle actual times (hours/minutes) without rather convoluted workarounds.
@Paul Newcome Is this still the case and l need a convoluted workaround to get how much time a generator was running?
Trying to calculate how many hours a generator run for, and for the cell to show as empty when there's no data in the cells. After reading a lot of posts came up with a formula but l can't figure out how to remove the "#INVALID VALUE" error, tried wrapping the formula in a "IF ERROR" but did not work.
This is my current formula, but there has to be something simpler and that allows for a cell to show as blank if both feeding cells are blank:
=VALUE(LEFT([Generator #2 Time Stopped]@row, (FIND(":", [Generator #2 Time Started]@row) - 1))) - VALUE(LEFT([Generator #2 Time Stopped]@row, (FIND(":", [Generator #2 Time Stopped]@row) - 1))) + (VALUE(RIGHT([Generator #2 Time Started]@row, (FIND(":", [Generator #2 Time Stopped]@row) - 1))) - VALUE(RIGHT([Generator #2 Time Stopped]@row, (FIND(":", [Generator #2 Time Stopped]@row) - 1))) / 60)
Screenshot of the sheet:
Thanks!
@Silvia Rangel That is correct. Smartsheet does not yet have built in time calculations. I will include a link at the bottom of this post to a thread that has numerous time based solutions in it.
As for the IFERROR, it should wrap around the entire formula like so...
=IFERROR(VALUE(LEFT([Generator #2 Time Stopped]@row, (FIND(":", [Generator #2 Time Started]@row) - 1))) - VALUE(LEFT([Generator #2 Time Stopped]@row, (FIND(":", [Generator #2 Time Stopped]@row) - 1))) + (VALUE(RIGHT([Generator #2 Time Started]@row, (FIND(":", [Generator #2 Time Stopped]@row) - 1))) - VALUE(RIGHT([Generator #2 Time Stopped]@row, (FIND(":", [Generator #2 Time Stopped]@row) - 1))) / 60), "")
@Paul Newcome Thanks! So, l realized l had a space between the end of the formula and the coma ( 60) , "") and this was giving me the error... Also, l tried the formulas in your ime based solutions post but none worked for what l am looking to do, at least for this sheet, as they worked for others! ☺
( 60)
@Silvia Rangel Glad you got that figured out. Are you still needing an overall formula? I would imagine a negative result for run time is not exactly accurate.
Hello, I face one difficulty trying to transform text in date using DATE formula I want to find the first day of a week based on the week number & year number put in a cell For instance in a cell I find "25-45" FOR Year= 2025 & Week= 45, so I look for the monday of this week that should be the 3rd of nov Step 1 find first…
I have a formula that I have used for years on a sheet and it was working an hour ago and then all of a sudden it just stopped working, I went out the sheet and back in and . The formula is =IF([Shop Order]@row = 0, (COUNTIF((RN:RN), RN@row ))) but instead of returning the value it says #INVALID COLUMN VALUE Got it working…
Okay, so I have been working this problem for a few days and it's officially making me crazy. Here's the problem statement: I have 3 intake sheets for different business units. Each has an Auto-Number column that has a prefix for the BU. I need to consolidate all of the attachments from those 3 sheets into 1 sheet. So on…