When adding a resource (Assigned To) and the % allocation on a task line, with subtasks, why will it not take the allocation percentage?
What formula are you using in the parent row to add the Allocation %, or do you have dependencies enabled in the Gantt View settings?
Thanks for your reply. No formulas. Yes, dependencies are enabled. When I enter a number, it just disappears and doesn't stay in the cell. Any thoughts?
When dependencies are enabled, whatever columns are being used for those dependencies, the parent rows are automatically considered a "summary row" of the children rows. Changes cannot be made to those cells to include using formulas and/or manual entry. Here is a link that should help explain things a little better. It is the page the link in the screenshot below sends you to.
https://help.smartsheet.com/articles/765675-work-with-gantt-chart?frame=0&nav=1
Hello, I'm working through the writing formulas optional activity and in the 'Nested IF function - Progress Column' task it directs you to put in the following formula '=IF([% Complete]@row = 0, “Empty”)'. However, when I put this formula into the spreadsheet, '04a_Marketing Request Tracker - Formulas', I get an…
I have an automation that has a condition where I am looking at the column "LEA Interco Supporting Site(s)" and trying to find columns that have the value "Fort Loramie" in them. This works well when "Fort Loramie" is the first item listed in the cell, but it doesn't work when "Fort Loramie" is the second or third value in…
Have any of you created a Smartsheet that would show the savings for a project by the month? In other words, if I saved $1200 annually and the project ended in say March, then the savings would go $120 per month, Mar 2025-Feb 2026. I have done it on Excel sheets manually, but I think there should be a way to do it with…