Currently I have the ability to manually add holidays to the Gantt view, which default as non-working days. I would like to be able to mark a calendar das a WORKING or NORMAL day, but still have it highlighted (in a color of my choice) on the Gantt view. Ideally, I could even add a description that would show if I move my…
Hi there, If you look at the attached image you can see the issue I'm having - the issue is that the line items colored GREEN should appear directly under the gray "Universal masthead design / Tone / Messaging" bar since they are indented in underneath it - see task list on the bottom of the attached image. Instead the…
Hello, Is there anyway to default dependences so that when you start a new project sheet the dependences are already set? I am currently setting up multiple projects and having to enter working weeks, hours per day and holidays is quite time consuming.
We have a need to add workdays excluded by persion option to our project sheet to accurately account for the duration. I can see you can exclude holidays but I want to exclude days off extc. Is there a way to do that?
HI All, When I look at Smartsheet created events shared to a Google Calendar from the computer PC/Mac I get a link that says: "Edit Smartsheet Rows". It brings up a popup window and then login to Smartsheet and the data shows just fine. Great Stuff! Problem is from an IPHONE/MOBILE DEVICE using both the IOS Calendar app or…
So I set my project so that working days are Mon-Fri. However I want to make an exception on a specific Saturday, and make that a work day. Is that an option?
Hello, We created a smartsheet and subscribe to the calendar using the publish to ical function. It displays correctly in Outlook, but when we try to set a reminder in the Outlook calendar it gives an error saving "the reminder for xxxx will not appear because the item is in a folder that doesn't support reminders". When I…
Hello - I've setup a webform for users to enter information about potential participants in a program. I want the form to automatically capture the date when the form is completed. I had initially set it up where I established a date field on the form but hid it from users. I thought by selecting 'Today' from the drop-down…
I have a Team Vacation schedule (the team is working in 4 different countries) and have also added dates for holidays which the company is also off according to the local holidays. Is there a way so that these holidays will show down the Gantt chart so that I don't have to always scroll to where the Holiday is set to see…
MS Project has the capability to maintain duration in days or weeks independently of work (hours). Does this capability exist in Smartsheet?