I'm trying to setup a sheet for tracking actual work dates vs target dates Construction Document set timing. In each deliverable/row I'd like to list the following dates:
• Target Date
- • Act Start
- • Act Finish
- • Approval Date
I have my the project settings turned on so that "Act Start" and "Act Finish" create teh Gnatt timeline with dependencies. So i can calculate the Actual work (duration time) with no problem.
The "Target Date" column is used to show the origional milestones, and I can compare it to the Act Finish to add in conditional formating, so no problem here.
What I can't seem to do is count the turnaround (or approval) timing, but subtracting the "Act Finish" date from the "Approval Date". I deally this woudl give me a count of working days, just like the duration column. But I can't find a formula that will do this, or a way to add a second "duration column"
Is there any way to do this?
Thanks