Hello,
I'm trying to use the system generated creation date as a start date for a range in calendar view. For some reason it's not recognizing the column as a "date" column?
Any ideas on how to make that work? Thanks.
- Eric
Create another column to use as the start date and set it =CreatedDate.
This will only work if Dependencies are not enabled.
If they are, the date columns used for start/end can not have formulas.