-
Generate Bar Code and link to cells
can we generate barcodes of each equipment and with the help of bar code scanner, can it display the information of it with the the options to update the forms? I know we can update the forms but how can we display the informations from the sheet at the same time?
-
Restricting Access to Linked Attachments?
In a sheet that I created and shared with other users, does every user have access to be able to open/view attachments linked to some rows if the user I shared the sheet with doesn't have access to the document in the original application (ie, Dropbox)? If so, is there a way to restrict access to the sheet attachments for…
-
Average for both columns
I have a dropdown columns with several choices and each choice represents % complete. The idea is to get the Circuit % complete for 1st and 2nd circuits columns but also It has ‘N/A” that will not count. It only count the column that doesn’t have it. This is what I tried: =AVG(IF([1st Circuit Status]@row = "Assigned to…
-
Invalid Operation when using Today() in nested IF STATEMENT
Here is the formula I am working with: =IF(ISBLANK([Start Date]@row), " ", IF(ISBLANK([Actual Start Date]@row), "Not Started", IF(ISBLANK([Actual End Date]@row), "In Progress", IF([Actual End Date]@row > TODAY(), "In Progress", "Complete")))) When I have dates entered for Start Date, Actual Start Date, and End Date the…
-
Is it best to link only one predecessor to each task or is it ok to have multiple?
I am working on a construction schedule and wondering what the best practice is for attaching predecessors. I have noticed my Gantt chart is currently a bit all over the place and I am thinking it is because I have too many predecessors for each task. Do more experienced Smartsheet users recommend only having one…
-
Create Chart Widget Using a Report (not a Sheet)
With the Dashboards, I am able to create charts from a sheet but not from a report (this requires using the report widget). I collect weekly "submission date" data from 40+ people. I have created a report that shows when the submission is due, when it is submitted, and the number of days (plus or minus) between the two. I…
-
COUNTIF with keywords
Hello, I am trying to set up a formula to count a cell if it contains a certain keyword (e.g. "communication"). The cell itself won't be only composed of that word, but will just contain it. My formula so far is =COUNTIF([Job Classification]:[Job Classification], CONTAINS("communication", [Job Classification]:[Job…
-
I imputed a date that was 09.01.22 and yet the png shows 01.01.22
I completed a gantt chart shown here and as you can see my start date is 09.01.22 and yet the gantt charct shows january february, etc., this is ridiculous and completely ruins my chart and I didn't even input those values. If anyone could help me in removing them I would be grateful, thank you.
-
Total Site % Complete + health
I need the total site % Complete Each milestone has % complete for the site project What is the sample formula to calculate each milestone % complete columns to give the site Total % complete? Let’s say, Milestone ABCDEF etc I just want to SUM all the milestone % complete to give me the total project % complete Then the…
-
How to overrule a 0 multiplication formula returning 0 as an answer?
Hi all, haven't been able to find anything on this by searching so I'm posting. I'm hoping it is a simple fix as the formula seems very simple! I am attempting to calculate accident frequency rates at my company. I fully understand that anything multiplied by zero returns zero. However, if there have been no accidents I…