Is it best to link only one predecessor to each task or is it ok to have multiple?

lbell
✭✭
I am working on a construction schedule and wondering what the best practice is for attaching predecessors. I have noticed my Gantt chart is currently a bit all over the place and I am thinking it is because I have too many predecessors for each task. Do more experienced Smartsheet users recommend only having one predecessor for each task? Thanks!
Best Answer
-
I would recommend keeping the predecessor column accurate (i.e. with multiple predecessors, if applicable) and then using a milestone or key activities report to view a simplified Gantt.
Answers
-
I would recommend keeping the predecessor column accurate (i.e. with multiple predecessors, if applicable) and then using a milestone or key activities report to view a simplified Gantt.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.7K Get Help
- 436 Global Discussions
- 152 Industry Talk
- 497 Announcements
- 5.3K Ideas & Feature Requests
- 85 Brandfolder
- 155 Just for fun
- 77 Community Job Board
- 508 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 37 Webinars
- 7.3K Forum Archives