Is it best to link only one predecessor to each task or is it ok to have multiple?
I am working on a construction schedule and wondering what the best practice is for attaching predecessors. I have noticed my Gantt chart is currently a bit all over the place and I am thinking it is because I have too many predecessors for each task. Do more experienced Smartsheet users recommend only having one predecessor for each task? Thanks!
Best Answer
-
I would recommend keeping the predecessor column accurate (i.e. with multiple predecessors, if applicable) and then using a milestone or key activities report to view a simplified Gantt.
Answers
-
I would recommend keeping the predecessor column accurate (i.e. with multiple predecessors, if applicable) and then using a milestone or key activities report to view a simplified Gantt.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives