Is it best to link only one predecessor to each task or is it ok to have multiple?

Options
lbell
lbell ✭✭
edited 09/27/22 in Smartsheet Basics

I am working on a construction schedule and wondering what the best practice is for attaching predecessors. I have noticed my Gantt chart is currently a bit all over the place and I am thinking it is because I have too many predecessors for each task. Do more experienced Smartsheet users recommend only having one predecessor for each task? Thanks!

Best Answer

  • Sam_Harwart
    Sam_Harwart Community Champion
    Answer ✓

    I would recommend keeping the predecessor column accurate (i.e. with multiple predecessors, if applicable) and then using a milestone or key activities report to view a simplified Gantt.

    Thanks,
    Sam

    Want to chat about a Smartsheet problem you're facing?
    Grab time on my calendar here:
    Smartsheet Community Chat

Answers

  • Sam_Harwart
    Sam_Harwart Community Champion
    Answer ✓

    I would recommend keeping the predecessor column accurate (i.e. with multiple predecessors, if applicable) and then using a milestone or key activities report to view a simplified Gantt.

    Thanks,
    Sam

    Want to chat about a Smartsheet problem you're facing?
    Grab time on my calendar here:
    Smartsheet Community Chat