Baselines for newly added tasks?
Hi, Is there a way to use the baseline function for any task that is added to the sheet AFTER the baselines have already been added. For example, the original timeline was 10 rows of tasks. We have 5 new tasks to enter into the timeline. The only option is to "Reset" the baselines, which I do not want to do since the data…
-
Adding New Task After Setting Baseline
Smartsheet Community: Once The Baseline is Set. It Would Be Nice to Have The Ability to Add New Tasks and for those Tasks to be Added to The Baseline without Re-Setting it. Today, I have to Manual Change All the Dates. This Drastically Increase human Errors and is Very Time Consuming.
-
IFERROR and MATCH Formula not pulling in formation - Prodactive S-Curve
hello, i came across a Video by Prodactive about S-Curves in smartsheet and so far everything has been working exactly as expected with one major exception; the "Actual" baseline. From the video and the downloaded examples, i used the exact same formula and referenced my sheet name versus what he had in his example. But…
-
Target Date vs Baseline in Project Management Office template
The project plan in PMO template have Target Start Date and Target End Date which seem to serve the same purpose as the Baseline Start and Baseline Finish. Are they redundant or am i missing something?
-
Baseline Varianz Meilensteine
Hallo zusammen, hat jemand eine Idee warum mir Meilensteine (Dauer 0) je nach Platzierung innerhalb einer Projektphase (Ende oder irgendwo; jedoch NICHT am Rand der Phase) mit unterschiedlichen Varianzen zur Baseline (1T/0) angegeben werden obwohl Datumsangaben Ende/Baseline-Ende jeweils gleich lauten? → Beispiel in Phase…
-
How to get project overall delay in days in Smartsheet with multiple sub-parent rows
Hi While we use the Baselines on the task level to see the delays per task, is there a way to grab the overall project delay in days and also show it in the Dashboard? I'm using multiple sub-rows (up to three levels) to host tasks into different workstreams. Example: TOP ROW [Level] Parent Row1 [Level 2] Task 1 [Level 3]…
-
How to get project overall delay in days in Smartsheet
Hi While we use the Baselines on the task level to see the delays per task, is there a way to grab the overall project delay in days and also show it in the Dashboard? Thanks for any prompt Regards /Marat
-
Using Smartsheet Baselines values
Is there a way to use a helper Column and Formula to turn a Smartsheet Baseline variance into a real number so I can get an average? OR is there a better way to baseline changes to end dates?
-
Baseline Duration and Predecessors
I'd like to create a column for Baseline Duration and Baseline Predecessors, along with the current Start and Finish Date columns, when I baseline a schedule. In the cases where new tasks are added/inserted, the baseline predecessors would have to automatically adjust for the new row number that the predecessor has now…
-
Undo Baseline
The feature to undo a baseline that was recently executed in error would be really helpful