Baseline Varianz Meilensteine
Hallo zusammen, hat jemand eine Idee warum mir Meilensteine (Dauer 0) je nach Platzierung innerhalb einer Projektphase (Ende oder irgendwo; jedoch NICHT am Rand der Phase) mit unterschiedlichen Varianzen zur Baseline (1T/0) angegeben werden obwohl Datumsangaben Ende/Baseline-Ende jeweils gleich lauten? → Beispiel in Phase…
-
How to get project overall delay in days in Smartsheet with multiple sub-parent rows
Hi While we use the Baselines on the task level to see the delays per task, is there a way to grab the overall project delay in days and also show it in the Dashboard? I'm using multiple sub-rows (up to three levels) to host tasks into different workstreams. Example: TOP ROW [Level] Parent Row1 [Level 2] Task 1 [Level 3]…
-
Adding New Task After Setting Baseline
Smartsheet Community: Once The Baseline is Set. It Would Be Nice to Have The Ability to Add New Tasks and for those Tasks to be Added to The Baseline without Re-Setting it. Today, I have to Manual Change All the Dates. This Drastically Increase human Errors and is Very Time Consuming.
-
How to get project overall delay in days in Smartsheet
Hi While we use the Baselines on the task level to see the delays per task, is there a way to grab the overall project delay in days and also show it in the Dashboard? Thanks for any prompt Regards /Marat
-
Using Smartsheet Baselines values
Is there a way to use a helper Column and Formula to turn a Smartsheet Baseline variance into a real number so I can get an average? OR is there a better way to baseline changes to end dates?
-
Baseline Duration and Predecessors
I'd like to create a column for Baseline Duration and Baseline Predecessors, along with the current Start and Finish Date columns, when I baseline a schedule. In the cases where new tasks are added/inserted, the baseline predecessors would have to automatically adjust for the new row number that the predecessor has now…
-
Baselines for newly added tasks?
Hi, Is there a way to use the baseline function for any task that is added to the sheet AFTER the baselines have already been added. For example, the original timeline was 10 rows of tasks. We have 5 new tasks to enter into the timeline. The only option is to "Reset" the baselines, which I do not want to do since the data…
-
Undo Baseline
The feature to undo a baseline that was recently executed in error would be really helpful
-
Reset Baseline Not Appearing for Admin Users
We're having an issue where the Set/Reset Baseline buttons are not appearing for Admin users. Is this a known issue or is there a setting we need to change so these appear in the baselines popup? Thank you! Note: We have tested multiple browsers for this. Users with a license can see and use the baseline set/reset buttons,…
-
Formula using project plan Baseline columns that may not yet exist as Baseline hasn't been set
I would like to put a formula in place for the health of milestones within project plans deployed as templates in a Control Center blueprint. The formula would work similarly to how it works in the Project Plan template provided in the Project Management Office template set available in Smartsheet. However, the template…