We're having an issue where the Set/Reset Baseline buttons are not appearing for Admin users. Is this a known issue or is there a setting we need to change so these appear in the baselines popup? Thank you! Note: We have tested multiple browsers for this. Users with a license can see and use the baseline set/reset buttons,…
Smartsheet Community: Once The Baseline is Set. It Would Be Nice to Have The Ability to Add New Tasks and for those Tasks to be Added to The Baseline without Re-Setting it. Today, I have to Manual Change All the Dates. This Drastically Increase human Errors and is Very Time Consuming.
I would like to put a formula in place for the health of milestones within project plans deployed as templates in a Control Center blueprint. The formula would work similarly to how it works in the Project Plan template provided in the Project Management Office template set available in Smartsheet. However, the template…
The project plan in PMO template have Target Start Date and Target End Date which seem to serve the same purpose as the Baseline Start and Baseline Finish. Are they redundant or am i missing something?
Hello! We have baselines set up on our sheet. Is there a way to show the variance visually, in the Gantt or new Timeline view - or is it only visible in that column as a number? Thanks!
This discussion has been merged.
Hi I want to know if there is a simple way of keeping a log of baselines, e.g. each time it is reset, the old baseline is logged, similar to version control. The idea is that at the end of a project (which underwent change control resulting in the timeline needing to be re-baselined) we will be able to review the changes…
How do I baseline new activities added to my schedule without it impacting the baselines already established for activities that had been in the schedule? My schedule is being populated in phases so new activities will be added over time. If I reset the baselines already established for work that was in the plan already,…
In the current state, we cannot set baselines from WorkApps unless we set the desktop view to grid view. This is not an ideal experience. Don't really want the project schedule in Gantt view at all times. This may spark the need for a second enhancement request related to being able to switch views in WorkApps, which…
Is there a way to configure smartsheet to automatically set baselines at certain milestones in a project? My thought with this is my project plan would automatically set a new baseline at 3 different milestones, I would end up with 3 sets of baseline date columns. This would easily allow me to go back on projects and see…