Formula help on RYG Balls for Baseline Variance

hello all

I'm struggling with this because the variance is in Days. I did a basic IF statement where:

if the Status = complete then Green,

and "nested if" if the Variance was < -5 then Red else Yellow.

It just turned complete things Green and everything else yellow, because the variance is in Days (eg. 1d or -2d not a read number)

Ultimate Goal is to put the health of the project on a report then Dashboard for Executive lead team. Schedule Variance is my first thought.

Thanks for any guidance!