-
Merged: Timeline Headers on Gantt Chart
This discussion has been merged.
-
Gantt View Date Options for for an Unlicensed User
I am able to change the Gantt view on the sheet to show quarters (instead of weeks). I have an unlicensed user with the level as "admin" and she is still seeing weeks instead of quarters and is unable to change her view to be quarters (says you need a license). Is there a way I can make the default Gantt view for ever…
-
Merged: Gantt Timescale Settings
This discussion has been merged.
-
Additional Symbols for Gantt Charts
At time of publishing, Gantt charts have the capability to display bars (length of time for a task) or a diamond (milestone). Are there any future plans to add other symbols to use, such as a star or a circle to call out other important moments in time while differentiating from milestone diamonds?Thank you!
-
Automatic Predecessor Adjustment
Hey All! I have a question about how to have predecessors or just tasks in a schedule to automatically update when they are moved in the schedule. I am trying to create a production schedule for our Sheet Metal shop and it is created with the fabrication packages released from the Eng Dept. Sometimes the schedule needs to…
-
Best way to create a gantt for compliance tracking?
So I am working on verifying around 2500 addresses for compliance of an ordinance. The plan is to send them an email, wait a week and then send them a mailer and they have two weeks from us sending the mailer to reply. Going to do this in batches of 25 addresses at a time. So I need a way to keep track of which addresses…
-
Restricted Task Dates in Office Timeline Pro+?
I use Office Timeline Pro+ to create all my corporate project timeline slides by importing source Sheets or Reports. Is there a way to show project timelines restricted by a certain date? For example, I want to show all tasks that are in progress as of 1JAN2024, regardless of the actual start date (e.g., if the start date…
-
Why dont non working days carry thru to other projects?
I ticked the box to apply to all of account but they dont show or take effect in other projects? What am I missing or did not do?
-
Task that lasts the duration of the project
I have a task I want to track that lasts the duration of each project. However, since the start/end dates can't be formulas, I'm wondering if there's another way to set this up in my template?
-
Formating the Gantt grid so it is easier to see?
I want to view the timescale in weeks but I am having a hard time distinguishing the week gridlines (weeks are too weak!) Any way to make these less subtle? The "by day" timescale has banded colours, at least for weekend days. Is there a way to band the weeks or months to also help visually distinguishing periods? (I mean…