Baseline Visual in Gantt or Timeline view?
Hello! We have baselines set up on our sheet. Is there a way to show the variance visually, in the Gantt or new Timeline view - or is it only visible in that column as a number? Thanks!
-
Critical path viewed when linked to a parent row
It would be nice to have the critical path show when linked to a parent row. I have a parent row (e.g. Testing) where the children (e.g. test 1, test 2, test 3,...) are performed in parallel & have the same finish date, so I often link the successor task(s) to the one parent row vs. each individual test task rows (can be…
-
Why don't I see the critical path?
Hello Community, I have predecessors and dependencies, but I don't really see a critical, summary or driving path even though I have clicked to show them. Can anyone tell me why? Thanks, Ashley
-
Merged: Gantt View Duration Zoom Levels
This discussion has been merged.
-
Adjusting a Gantt view time for half day
Good afternoon, Is it possible through either setting a specific duration or formula to begin a task in the afternoon of a Monday and end at the end of day on Tuesday? I am creating a high-level view of an upcoming store project where some tasks beginning in the PM and finish the following AM and other tasks that start in…
-
Bookend a scheduler task with two predecessors & variable number of days
My smartsheet scheduler task will float between two predecessors… meaning it will start at the same time as one task (i.e. 10SS) and finish in coordination with another predecessor (i.e. 12FF). The number of days will technically be variable and change as the predecessors change. Smartsheet does not seem to allow this, but…
-
Starting with a Sheet, that Now needs to be a Gantt - how does one get roll-up summary info
We started with what we thought was going to be a simple sheet that has grown and now had Target Start and Target End date columns. Now we look at is as a Gantt (again not started as a Gantt sheet) So we made parent and child rows, have the settings in Gantt view looking at these date columns. However, if you indent/make a…
-
Dates start flashing after updating another task's predecessors
I have a project plan that I am now updating to establish dependencies. Everything was going fine until I updated one task's predecessors and a completely separate row's dates (and associated span in the gantt chart) started flashing. I'm guessing that there is some circular logic or something that might be causing this…
-
Merged: parent timelines when dependencies are enabled gantt Bar formatting
This discussion has been merged.
-
Project Collaborators Schedule Report
Hello everyone, I hope you're doing well. I'm new to SmartSheet and currently working on my initial projects and automations. I have a project group and would like to create a report in the project management office that allows me to identify all the collaborators involved in each project and in which months they will be…