-
Grid to Card View
Is it possible to create a project plan in Grid View and have it seamlessly transfer to the Kanban board on Card View? The hierarchy on the Grid View impacts the display of cards on card view. See attached screenshots. Ideally, I want to enter the project plan in Grid view and then have all the tasks show as cards in Card…
-
#Invalid Operation - Error
I have a issue that I just can't figure out. I have 2 identical Smartsheets one was saved as new from the other. I have the same formula in the same column in the 1 Smartsheet example I get a #INVALID OPERATION (Red Arrow) however in the 2nd Smartsheet example (Blue Arrow) the formula works In the attached I have provided…
-
Formula for a Flag Column Based an If/Or statement
I'm trying to write a formula using an IF/OR statement to set a flag (for the Revised Timeline column) when NA has been selected from a drop-down menu in the any one of five columns (e.g., Reason for Revised Analysis End Date). The flag should turn red when anything other than NA is selected. If NA is selected, then no red…
-
Creating a Master Sheet Composed of Dependent Dept Sheets // Sheet Linking // Sub-Sheets
Hi Community - Looking to crowdsource the best method of creating a Master Sheet (think: Company ALL) composed of smaller Department Sheets (think: Marketing, Development, etc). The ideal set up here is that while only I may have access to the the "Company All" the dept heads have access to their respective Department…
-
Formula for multi-cell status update
Hi all - First Discussion here. I am trying to use a formula that will populate a cell with "Not Started", "In Progress" or "Completed" based on the condition of eight cells in the same row have data in them or not.I have created two formulas that work in part but cannot figure out how to properly combine them.The idea is…
-
IF () formula, Change Status Dependate on Date
I would like to build a formula so that status will change to "Red" and type will change to "Renew" when date is past "Expire Date". I've applied the two formulas separately at the top of each corresponding column. But so far it just changes it to Red or Renewed automatically, without the date dependency. Can I make this…
-
Blank display value for Symbols type?
I'm trying to recreate a switch function I've used in Project files to work in Smartsheet. It updates a symbol status column based on %Complete, Today's date, and Finish dates. I'm trying to use the green Up, yellow Sideways, and red Down arrows. Issue is, also need to display a blank in that status column if none of the…
-
Date Formulas
Is there a way in data matrix to do a formula to count the the number of lines with a due date today to 30 days out? I am trying to see item that will hit in the future.
-
Double dependencies
I am trying to create a complex schedule. I have multiple tasks that feed into two different predecessors but only one is recognized. Is there way for these tasks to both be recognized?
-
Count Check marks across columns
Hi I'm relatively new to SmartSheet and have a question. I have a set where each row represents a requirement. Each requirement may impact multiple systems. Since I'm unable to select multiple entries with a drop down - I've created 4 column - each representing an impacting system. I now need to summarize in a dashboard…