Auto move column info
I'll try to explain the best I can. I have a customer who will view only a summary sheet in Smartsheet. This info is pulling from various cells in individual Smartsheet store pages that they cannot see. This summary is set up in a "One store per Column" arrangement. As the store page info is populated, various info…
-
Gantt chart, how to color weekends in OTHER colour than grey?
I have seen some post regarding the possibility of changing the colour of the columns marked as "non working days" and all suggestions to solve this seems to point to the possibility to change the colour of rows. So, I am again asking about the possibility to change the the colour of columns to enhance the readability of…
-
Submitted Web Form - User Information
We are creating a web form to track business development possibilities. Other than adding a "Your Name" field to our web form, is there a way to see who submitted the form? On a current smartsheet where we are using a web form, I can right-click to view history, but it shows only "web form user". What we would like to see…
-
Sheet automatically scrolling across as soon as I place mouse in sheet.
I have one sheet (that is shared) that automatically scrolls across to the right of the screen as soon as I place my mouse in it. I can not manually correct it back to centre or to the left of teh screen so i can read the data in it. My other sheets are not affected, and are working fine. Can you please recomend a remiedy.
-
Working with Multiple Calendars, Vacation Days, and Weekend working days
In my project team, we have team members located in different parts of the globe. I need to link to the project non-US calendars and holidays aside from those of the US. Additionally, I need to enter the vacation days of all team members who has vacation plans or out days, and enter weekend working days when, say, a…
-
RYGB Formula
I'm trying to get a RYGB formula to work. I'm thinking my order is wrong but I'm not sure. I had it working for RYGG but was asked to show Completed Tasks in a different color. I would like to change this so that Blue = Complete and N/A and Not Started are blank. Formula that is currently working for RYGG: =IF(Status@row =…
-
effort and allocation-based timelines?
We have a small team, with each member having very a specific area of expertise. As such, our timelines are defined by prioritization of tasks, dependencies, effort, and resource allocation. I want to enter my tasks, set their dependencies, effort in hours, priorities, plug in the resources and set their allocation, and…
-
Count number of resources per project
Hi, I'm trying to count number of resources assigned to a project but I'm not sure how to go about it, when there is a duplicate. Meaning, if John Doe is assigned to 5 tasks, Jane Doe is assigned to 3 tasks, and Billy Bob is assigned to 1 task, is there a way to count the number of resources assigned to the project, which…
-
Calculating Count of Projects by PM by Month
Hi, Trying to create formula to calculate How many projects start in a certain month by each Project Manager - My excel formulas are weak Master sheet has columns: Project Manager is Contact List (does this have to be a Text/Number Column?) Project Start Date - is Date type Column =COUNTIFS({Keller Project Summary - MASTER…
-
Formula for finding the first and last days of a year
I need to be able to calculate the first and last days of the year based upon the current date. Can someone help me out?