-
Is there a way to add sheets to multiple reports at the same time?
Hi, I have set up a bunch of different reports across multiple sheets. These reports include 'Tasks Due Soon', 'Overdue Tasks', 'Tasks Assigned to X', etc... Many of the sheets we have created use the same template (Standard Project Template) so that they work consistently with reports, but some of our sheets have…
-
Conditional Formating between 2 dates
I know how to achieve this in excel but can't figure it out here. We are looking to highlight a cell (or row) if the number of business days between two cells is less than 3 business days For example in a row we have: Date1 = 11/30/15 Date2 = 12/2/15 In this case above we would want to color Date2 red (or the whole row)…
-
Account Settings/Working Days
Good morning, Just wondering if there's an upcoming enhancement for perhaps a drop-down box to select your country where it will auto-populate major holidays, such as New Year's Day, Christmas, Thanksgiving, etc, but also allow to add additional days, if needed. Blessings, Loann
-
I want to add sprint into my agile project plan
How do i add extra sprints?
-
Color Coding for Past Events
Hello! New Smartsheet user, and trying to figure out this awesome tool! Let me start with a basic question: So, we are using a Calendar of Events to help keep us on track for events that we have occuring here at our minor league ballpark. I'd like to be able to highlight events that have past already. I know in Excel it…
-
Gantt dependency Start/End Dates not populating?
I have a Gantt Chart with dependencies enabled. When I shift the entire start date of the project all the dates shift appropriately so I believe it's working well. I've just inserted a new row and assigned a Predecessor Row and Duration. The bar appears to the right and dependency lines are drawn. However the Start and End…
-
smartsheet realtime co-authoring
Can we work at the same time on different records.
-
Formula to calculate count of checkboxes in multiple columns and child rows
Hi Everyone, I'm trying to write a formula that adds up the number of unchecked child rows in the Complete column and then subtracts the number of checked rows from the Non Applicable column. The result should be a number of tasks left to be completed from within that parent and child section. I've tried a bunch of…
-
Recruiting Metrics
Hi SmartSheet Fans, Wanted to start a discussion with the community revolving metrics and how you've used SmartSheet to get you recruiting metrics (time to fill, 1st touch date, etc.). Since everything is date related we created formulas to help us, but would love a different approach if anyone has any. Thanks! Kris
-
SETTING REMINDER DATES
Hello to all, I'm completely at a lost with formulas in Smartsheet because they are based on column name and location rather than cells like typical spreadsheets. The examples I find in the help are never similar to what I need, can someone help me please? We have a column for Date of Request and Due Date. Reminders are…