-
Date Modified
I have a sheet with a list of assets. There is a pull down menu that defines the status - I need to know when the menu is set to "complete". I can do that easily with a filter - but I want to cull the entries before a specific date. I have a Report that uses the 'is greater than-date modified' but I get results from all…
-
Estimate Date Planned against the target date
I need to calculate the planned date against the Go-Live date for each column. The dates are above the columns that should be prior to the Go-Live Target which is 10/31/22. I need to make the actual columns cells yellow for 3 dates against the planned date, red at the planned date. If a date is entered in actual column,…
-
Count time between dates in Weeks/Days
How would I calculate the time between two dates (start and finish) in Weeks and Days "8weeks 4days"
-
Match all columns to complete
I have several columns with dropdown (Complete-Go, Incomplete, TM Approved-Go) and one column that says (Go/No Go). If all columns have "Complete-Go or TM Approved-Go" the column (Go/ No Go) should be "Go" If any column has "Incomplete" the column (Go/no Go) should be "No Go" I appreciate your help very much! Rob
-
How to put a value for each item in dropdown list
I have a dropdown list and I want to put a value for each item (but not in the list): Not Ordered = 0% complete Ready to Order = 1% complete Order Process = 20% Shipped = 50% complete In Country Customs = 80% complete Delivered = 100% complete Cancelled = 100% complete This is to help me to calculate the task % complete…
-
Conditional Formatting Duplicates
Hello, Is there a way to conditionally format duplicates if a value is in a column and if a box is checked? I need this to look through the whole sheet where there are many input values by the customer via a form. Thank you. Brian
-
How do I count the entries from a column from another smartsheet?
I need to count total entries from another column from another smartsheet minus out scope criteria. i.e. 1st Smartsheet, column 1 Title “Total Sites in Scope” 2nd Smartsheet, Column 1 Title “Site IDs” that has entries. Column 2 Title “Order Status” dropdown option “out of scope” Solution: 1st Smartsheet, column 1, cell 1…
-
How do I make the cell to change data after other cell is populated?
I have sheet 1 with the rows below with formula in: LAN Migration Ready =COUNTIF({sheet 2 name Range 10}) LAN Migration Ready Approved =COUNTIF({sheet 2 name Range 11}) LAN Migration Scheduled =COUNTIF({sheet 2 name Range 12}) LAN Migration Complete =COUNTIF({sheet 2 name Range 13}) Sheet 2 I have: Each row represents a…
-
Status Rollup to Parent
I've seen some very similar solutions to my problem, but not quite what I am looking for. My Smartsheet plan has a status column and is using dependencies. My choices in the status column are (Not Started, In Progress, At Risk, and Complete). I would like to create a formula that automatically rolls up the parent of each…
-
Process Steps with fixed start dates and predecessors
I have a project timeline that has a manufacturing step that is contracted to start on a specific date in the future. This manufacturing step has predecessors, but changes in the timing of the predecessors will not change the date of the start of manufacturing because there was enough lag time built into the schedule to…