-
How to match clinical trials to subjects based on eligibility criteria columns?
Hello, I have 2 sheets and I want to pull information from sheet to another sheet if certain criteria are met. The first sheet, "Slot List", is a list of clinical trials and the columns contain the study name and certain eligibility criteria patients need to meet to join the study. On the second sheet, "Trial Match", is a…
-
Does Smartsheet's offer something like MSFT CoPilot
Is there any AI assistance available in Smartsheet's?
-
How to have users only able to see and edit rows assigned to them?
Hi We have a number of sheets spread over different workspaces. We only want the users to be able to see and edit tasks allocated to them. We do not want them to be able to see information on sheets that is allocated to others. Initially I thought that I could set up a sheet(s) and allocate rows to a specific user. I was…
-
Baseline vs Target Dates
Hi, In the PMO template we have both baseline and target dates. What is the difference between these? The target date seems redundant. Thanks
-
#INCORRECT ARGUMENT SET on Index/Collect Formula
I'm building a dynamic dashboard with multiple filters. I'm making a Index/Collect formula that can read values on a source sheet based on the values selected via the filters. This formula should work and I've seen it work on other sheets that Pro-desk helped with, and they gave me, but for some reason, I'm getting a…
-
Formulas not updating when new data is added to underlying sheet
When new data is added or updated to the underlying sheet, the formulas are not recalculating. I run an upload workflow each morning and want the metrics sheet below to recalculate based on the updated report I attach. I have to manually re-enter the formula to get an updated metric. The counts, averages and formulas using…
-
Is there a way to set a constraint on a task's Start Date that can override a predecessor?
We have migrated a fairly complex plan from MS Project to Smartsheet and have been able to line up most of our dates. However, when Predecessors finish early on a task, the start date is impacted, as expected. In MS Project we can use constraints to say the next task cannot start early even if its predecessors end early.…
-
Trigger a monthly approval automation?
Hi there, A team keep track of hours worked per project on a sheet that looks like this. I'd like to trigger a workflow that sends the project manager an approval request on the first date of each month to approve the work completed the month prior. However, I do not want the project manager to get separate emails for each…
-
Add Latest Comment Column without creating a comment
When creating a Grid, need the ability to add Latest Comment in Grid view without having to add a comment first. Thank you.
-
Copy/ Paste Cells With Multiple Lines Doesn't Work
I've been digging through community for resolution to this issue, but I'm coming up empty. I need to be able to copy/ paste multiple rows of data that have "multi-row (alt+enter)" information from Excel (and Smartsheet). Currently, when I try to copy and paste these "multi-row" cells, they spill into separate cells instead…