For my Project - The team currently have 15 separate workstreams tracked in individual sheets, each over 1,000 rows. While this setup has worked so far, we're starting to encounter some challenges:
Difficulty managing cross-sheet predecessor logic, requiring manual updates in each sheet
- Inconsistencies and versioning issues with data spread across so many sources, though we have same standardized columns
- Nearing the 20,000-row limit in several of our larger sheets, if merged as Integrated Master Schedule.
- Lack of a unified view for executive reporting and analytics
We're considering consolidating all 15 workstreams into a single master sheet/ data table to streamline reporting, simplify cross-project logic, and give us room to scale. I'm aware this is a significant structural change that will require careful planning and execution to maintain existing predecessor relationship.
Want to check if anyone has done it?
- Are there established methodologies or tools for merging large sheet data while preserving a core workflow logic like predecessors, when we move 15 sheets to 1 integrated schedule.
- What API operations and safeguards should we consider for safely moving subset data into a unified structure, if any
- Are there alternatives we should consider to a single consolidated sheet, such as Data Table as merging them together will exceed 20K limit.
- How we can move data preserving the current predecessor.