Hi guys, any advise on how works with % completed vs planned % completed as smartsheets only has column for % completed?, has anyone achieved to make a similar column for planned %?
Hello,
You can create a new text/number column in your sheet and format it for percent. Details on formatting columns for percent can be found in our Formatting Options help article.
If you need planned percent complete to be calculated for you, you'll need to create a formula in Smartsheet that does this. You can find the complete list of functions here: https://help.smartsheet.com/functions
Hello Smartsheet Friends! I recently switched jobs and once again working at a company that uses Smartsheet (hooray!). That said my skills are a little rusty, and I'm struggling with a basic update request automation. I've added a checkbox column titled 'Product Owner Update'. The intent, is that when a user checks the…
Hi My team have a list of projects they are working on. I want to prompt them for a weekly update that will ask them to populate these fields - RAG Status , Progress this week , Plan Next week, Risks/Decision/Issues , Details Then i can create a dashboard showing only this weeks info but i have the repository in the back…
How to use Smartsheet AI/automation to automically write project status?