I am creating a basic task check list that restarts every 4 weeks. I would like to set a task for Day 1 and automatically set all of the future task due dates based on lag time. I am not using predecessors.
I would appreciate suggestions.
Hi,
Please see attached link/screenshot. (The - sign should be
I hope this helps you!
Best,
Andrée Starå - Workflow Consultant / Get Done
If you want those dates to be based on weeks, you would want to calculate it in days. =date1+7 is for one week past due date, and for two weeks you would use =date1+14.
To speed the entry of these formulas, you can (and should) use absolute referencing, like this:
=[Target Date]$1 + 1
=[Target Date]$1 + 2
Two cells can be selected and dragged down to increment them. Since that will run into weekends too, I would add another column for the lag (Text/Number)
Then the formula becomes
=[Target Date]$1 + [Lag]@row
Craig
Anyway we can make this view only for security purposes? We would like to prevent users from sending responses to other users by accident.
I am currently setting up an automation for people to get notified through their email, when they are prompted. But is there a way that they can reply in the email of a comment that will then go to the specific sheet. This way they do not have access to the sheet, but can just comment through email with updates?
Is there a way to revert to the old dashboard look and feel. The new dashboards do not look good at all. There is no way of knowing if there are additional items in the widgets until you scroll over one to learn there is more to it since the vertical bar doesn't show. We have hundreds of dashboards and they will all need…