I have a report pulled into my Sight. It's pulling in a number of blank lines along with the correct data. It causes problems when I want to sort alphabetically because all the blank rows are on the top. Any ideas? Thank you for your time. PC
Smartsheet automatically adds blank rows to your sheet. But sometimes those rows gather data (like formulas) that you've added. Try deleting all of the blank rows in your sheet, saving, and then run it again.
Thank you! Yep, I have lines below the data that include formulas. I figured that might be the problem.
You're welcome!
How to use Smartsheet AI/automation to automically write project status?
Hi there, I have just recently worked with Smartsheet's Implementation team to build a Control Center Blueprint. The workspace that holds the solution is titled something very generic and I would like to rename it. Can I do that w/out breaking anything or what steps would I need to take to successfully rename it. Thanks in…
I'm looking for a way to attach notes to a sheet that isn't attached to a specific row. Rows for many of my sheets are cleared out in preparation for the next iteration of the project, and I need a notes/comments field that remains with the sheet even when the rows do not.