I want to track how long an open task is delayed on a project
Hello,
You might be interested in using the baseline method to track planned vs actuals: https://www.smartsheet.com/blog/quick-guide-mimicking-baseline-functionality-smartsheet
Hi,
By how long you mean:
How much diff there was from the initial due date?
or
If a task is not completed, how much time past from the due date (meaning Today - Due date)?
How long has past since a task is considered delayed (time that past since status was changed to "delayed", etc.)?
or, something else?
Sorry, I was out of the office. I would like to track: If a task is not completed, how much time has past from due date and also track due date changes (the difference between the original due date and new due date) open task only.
Hello community, What can we do if I cannot delete the data shuttle workflows that I created myself? Thanks!
Hello, I have created a dashboard and added some Metric Widgets to my dashboard that is pulling text from the profile data sheet that I created. However, on the screen shot below, where it is pulling information into, I want to change the formatting (no bold, smaller font). But when building the dashboard, it doesn't let…
Hey, in the smartsheet we have been working on, user can create work orders and that will get displayed in the application. so one action performed recently was using the option 'Copy to Another sheet' for a set of multiple rows and deleting them later in the source sheet , due to this it caused 404 errors for all the rows…