I would like to create a milestone where it is within a timeframe I decide to setup. For Example if I put the Start Date as 5/15/18 and a target date of 5/23/18 how can I go about doing this so we can see a milestone.
Milestones are created by using 0 in the duration and having a start date.
https://help.smartsheet.com/articles/516406-creating-a-milestone
Hi Justin,
Further to Mike's solution, you could link the milestone to your task using the Predecessors column. This way your Milestone would shift when the Finish (Target) date is updated.
Kind regards,
Chris McKay
Thank you for the information
Thank you for the follow up information
Great suggestion Chris. I hate it when the tasks move but the milestones don't.
Even deleting the name does nothing…even if I hit save it comes back…help!
Yesterday it was brought to my attention that on 9/2, a bunch of rows in a sheet I manage had randomly been updated. The Activity Log isn't very helpful to troubleshoot, but it appeared based on spot checking that it had impacted rows that were 'closed requests' so I added a condition to all my workflow rules to NOT change…
This may be a longshot, but I am wondering if there is an easy way to track what a delay is within a project? My best thought would be to make it a manual field within sheet summary that is a dropdown. It would be called something like Project Delay with dropdown selections like: Customer, Supply Chain, Sourcing, etc. Not…