If you are familiar with MS Project, you are aware of the Reschedule Remaining Work functionality. Does this type of feature exist in Smartsheet? If not, what is used to "push" out work not completed to determine the new end date?
HI, nothing in the system will do that other than manual intervention to eg increase the duration to the delayed task/s or if it hasnt started at all to move the start date back. All manual I'm afraid.
Mick
Is there a way to revert to the old dashboard look and feel. The new dashboards do not look good at all. There is no way of knowing if there are additional items in the widgets until you scroll over one to learn there is more to it since the vertical bar doesn't show. We have hundreds of dashboards and they will all need…
When i try to send or print the timeline view instead of showing the progression bars like they do on the screen it only send the data entered and not a graph type view to print. Is there a way to do this. I am using a mac platform if that helps.
I have reproduced the following behavior in a validated Smartsheet application. User permission: Editor (not Admin) Row status: Locked (confirmed via row menu displaying "Unlock Row") Text, Date, Contact List, and Checkbox columns cannot be modified. Dropdown List columns remain editable. Selecting a new dropdown value and…