Hi,
I would like to assign a resource to a project but the user name not appear on the enterprise list or my contacts list. If I add the user to my contacts don´t appear on the resource view.
What could I do for this?
thanks for your support
To be shown on the Resource View:
1. user must be a user in your account (licensed or unlicensed, can be invited but not accepted)
2. Sheet with the task must have Resource Management enabled.
Craig
Hi, I have a very simple automation set up where if the box is checked, change the dropdown column for that row to COE Team. I tried it and it didn't work. I waited for about an hour to see if it was taking a long time but it still is not working. There is no formula involved with the automation so it would be a manual…
I was archiving critical accounting data from one sheet to another by moving the rows. This is something I've done countless times in the past decade of using Smartsheet. This time, after moving nearly 3500 rows of data, I realized none of the attachments moved with the rest of the data. I've opened a case but have had…
Hi Team Is there an update on this Community post from a year go? Issues with copying in the Windows App - Table View - Smartsheet Community I have confirmed in both Desktop and Web Applications, and on multiple browsers where the Clipboard setting in "ALLOWED", but the copy/paste CTRL-C/CTRL-V is not working. It doesn't…