Hi,
I would like to assign a resource to a project but the user name not appear on the enterprise list or my contacts list. If I add the user to my contacts don´t appear on the resource view.
What could I do for this?
thanks for your support
To be shown on the Resource View:
1. user must be a user in your account (licensed or unlicensed, can be invited but not accepted)
2. Sheet with the task must have Resource Management enabled.
Craig
I'm looking for a way to attach notes to a sheet that isn't attached to a specific row. Rows for many of my sheets are cleared out in preparation for the next iteration of the project, and I need a notes/comments field that remains with the sheet even when the rows do not.
I have a workspace that I am looking to move items from into a new workspace. The reason I want to do this is becasue there are individuals that have access to the original workspace that do not need access to everything that is currently in the workspace. In the original workspace is a MAIN document that holds all…
How to use Smartsheet AI/automation to automically write project status?