I am building a project that has external dependency to be delivered on a specific date . How do you create this dependency? Do you create a task with no duration? (start and finish date are same)?
For me, it depends on where the external dependency is stored / maintained.
If it is located in another Smartsheet sheet, you can link a date to the [Start] date of the project but not the [Finish] date. At that point, either the task is 0 duration (if tied to a [Finish] date or something else if tied to just a date or the [Start] date.
If the external dependency is stored external, I'd probably have a short task to check on its status or react to a trigger, but that is likely best modeled as 0 duration task - the milestone is the external dependency.
Craig
I'm looking for a way to attach notes to a sheet that isn't attached to a specific row. Rows for many of my sheets are cleared out in preparation for the next iteration of the project, and I need a notes/comments field that remains with the sheet even when the rows do not.
I have a workspace that I am looking to move items from into a new workspace. The reason I want to do this is becasue there are individuals that have access to the original workspace that do not need access to everything that is currently in the workspace. In the original workspace is a MAIN document that holds all…
How to use Smartsheet AI/automation to automically write project status?