I am building a project that has external dependency to be delivered on a specific date . How do you create this dependency? Do you create a task with no duration? (start and finish date are same)?
For me, it depends on where the external dependency is stored / maintained.
If it is located in another Smartsheet sheet, you can link a date to the [Start] date of the project but not the [Finish] date. At that point, either the task is 0 duration (if tied to a [Finish] date or something else if tied to just a date or the [Start] date.
If the external dependency is stored external, I'd probably have a short task to check on its status or react to a trigger, but that is likely best modeled as 0 duration task - the milestone is the external dependency.
Craig
Hi, I have a very simple automation set up where if the box is checked, change the dropdown column for that row to COE Team. I tried it and it didn't work. I waited for about an hour to see if it was taking a long time but it still is not working. There is no formula involved with the automation so it would be a manual…
I was archiving critical accounting data from one sheet to another by moving the rows. This is something I've done countless times in the past decade of using Smartsheet. This time, after moving nearly 3500 rows of data, I realized none of the attachments moved with the rest of the data. I've opened a case but have had…
Hi Team Is there an update on this Community post from a year go? Issues with copying in the Windows App - Table View - Smartsheet Community I have confirmed in both Desktop and Web Applications, and on multiple browsers where the Clipboard setting in "ALLOWED", but the copy/paste CTRL-C/CTRL-V is not working. It doesn't…