Connect with peers, share your expertise, and inspire what’s next in Smartsheet — from proven practices to practical how-to insights from fellow users and product experts.
Sign in to join the conversation:
Is there a similar function to PMT? =PMT(rate, period, pv, fv) etc? Have not been able to find one. Thank you.
Hi David—
There isn't a similar function to PMT in Smartsheet.
You may need to consider storing the values (rate, nper, pv, [fv], [type]) in specific cells and then manually calculate with a formula.
This is equation with 4 columns (ignoring two optional args in PMT)
=(Pv@row * R@row / IntPer@row) / (1 - (1 + R@row / IntPer@row) ^ (-n@row * IntPer@row))
R = APR %
Pv = present value
IntPer = interest periods per year
n = term in years
Craig
Hi All,
I have the same requirement to re create the excel formula "PMT". The above formula does not include the future value and type aspects.
Also the Amortisation Template in SS doesn't line up with the required calculations either.
Trying to build a quote calculator for our customers to use.
The file attached shows the working out of the Excel formula.
Excel formula =PMT(rate,nper,PV,[FV],[Type])
The PMT function syntax has the following arguments:
Any help would be greatly appreciated!!!
This has ALREADY been solved by Mr Williams above but thought this might be useful for someone else to visualise it...
Using the above I initially created helper columns named the same as the references in the formula
Then realised what it was doing and made the following formula from the entries in a single column called "Loan Values":
=ROUNDUP(SUM(($[Loan Values]$4 * [Loan Values]2 / 12) / (1 - (1 + [Loan Values]2 / 12) ^ (-$[Loan Values]$3 * 12))), 2)
(Works with or without absolute references "$". The Yellow cells are my User Entry variables. Work in progress)
The "12" is the number of months in a year just in case that wasn't clear.
Also, I used another one of Mr Williams' tips from another thread for the Date. Using a Date column type on the far left, I then used:
=([Start Date]@row + "")
This displays the "date" as plain text in my loan values column. The end date is then worked out automatically using this formula:
=([Start Date]7 + SUM([Loan Values]3 * 365) + "")
Why? because when I create a report for display on dashboards I will exclude the Date Column for a neater look.
ROUNDUP to 2 places is also used BUT not needed really.
The layout is inspired by a free Microsoft template
Nice work @ON_Again
@J. Craig Williams
I don't suppose you happen to have a Smartsheet solution set up for present value (PV). I'm looking at this excel explanation and am at a loss of how to recreate it in Smartsheet.
Thanks,
Is there a way to revert to the old dashboard look and feel. The new dashboards do not look good at all. There is no way of knowing if there are additional items in the widgets until you scroll over one to learn there is more to it since the vertical bar doesn't show. We have hundreds of dashboards and they will all need…
When i try to send or print the timeline view instead of showing the progression bars like they do on the screen it only send the data entered and not a graph type view to print. Is there a way to do this. I am using a mac platform if that helps.
I have reproduced the following behavior in a validated Smartsheet application. User permission: Editor (not Admin) Row status: Locked (confirmed via row menu displaying "Unlock Row") Text, Date, Contact List, and Checkbox columns cannot be modified. Dropdown List columns remain editable. Selecting a new dropdown value and…