Good afternoon.
I have a question about the percentage during the project, because my% predicted on the date and my% Complete, does not hit when they are the same.
I think your formula aide is hiding part of the answer.
There are a couple of different factors at play here.
1. [% Complete] children are entered manually. Unless your manual entries match the predicted, they will diverge.
2. If you check rows that are supposed to finish today, since you use greater than instead of greater than or equal to, you may get odd results because the End Date for today is (probably) at the end of the work day, which may or may not line up with the value returned by TODAY()
3. [% Complete] roll up is based on the sum of the individual durations and your prediction is based on the start and end dates. If there are any gaps or overlaps, the two numbers will diverge.
There's more, but should get you started.
Craig
Hi, I am wondering if there is a solution for this scenario: I have a Data Shuttle data upload workflow to a Target Sheet that is updated when a new attachment is added. Question: is there a function/features/workaround like Data Shuttle, Bridge, or a combination of features so that if a new column is added to the Excel…
I have downgraded to business but no longer have access to my sheet,i get an error 48,get licensing? How do I fix this? This is a customer contact form so i cant recreate it as the email has been sent?
I have been given access as an Admin to edit an existing sheet but cannot edit columns. I am a System Admin. I am a paid Member. I am able to edit information in the sheet but cannot add a column.