I have imported a checklist from excel, set it up as a Gantt (transposed columnar hierarchy,) put in predecessors, and durations. No bars appear on the chart. What's up with that?
Hugh As your sheet is based on an import and conversion from Excel.....
i'd check your column properties especially your Start and Finish dates columns and do a little due diligence, there must be a small error you haven't spotted?
Good luck!
Richard R
Despite due diligence to this point, including asking this question, I'm quite sure that the issue is on my end. I do have start and end dates set as date type. Is there a list of required columns and settings for a Gantt Chart?
This article explains how to add a Gantt chart to a current sheet. Hopefully, this will help!
https://help.smartsheet.com/articles/765675-work-with-gantt-chart
I was archiving critical accounting data from one sheet to another by moving the rows. This is something I've done countless times in the past decade of using Smartsheet. This time, after moving nearly 3500 rows of data, I realized none of the attachments moved with the rest of the data. I've opened a case but have had…
Hi Team Is there an update on this Community post from a year go? Issues with copying in the Windows App - Table View - Smartsheet Community I have confirmed in both Desktop and Web Applications, and on multiple browsers where the Clipboard setting in "ALLOWED", but the copy/paste CTRL-C/CTRL-V is not working. It doesn't…
I have a user that has accepted their invite. They do not show up in the roles section for me to assign the user roles.