My duration roll ups for child/parents are not working as expected. Can anyone advise of things I could try to resolve why only one parent has a duration total?
Hi Paul,
Start with checking your Project Settings (Right-click on any column and select Edit Project Settings).
Edit: You must have durations and dates for the parent to show the total duration.
Did that help?
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I had the project settings on, but turning off and then back on worked!
thanks
Great!
Happy to help!
Andrée
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…