My duration roll ups for child/parents are not working as expected. Can anyone advise of things I could try to resolve why only one parent has a duration total?
Hi Paul,
Start with checking your Project Settings (Right-click on any column and select Edit Project Settings).
Edit: You must have durations and dates for the parent to show the total duration.
Did that help?
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I had the project settings on, but turning off and then back on worked!
thanks
Great!
Happy to help!
Andrée
Hello everyone, I'm building an automated Above Ceiling Work Permit process for our hospital and have almost everything working. I'm hoping someone can tell me if the final step is possible using native Smartsheet features. My current workflow A contractor scans a QR code and completes a Smartsheet Form. The form creates a…
I am using the new "linked" column for a dropdown on my sheet. Is there any way to sort the dropdown options? I have sorted them on my source sheet, however it doesn't update in the dropdown.
I am building out my sheet summary from a schedule. I have a Parent Row column and all of my parent rows have a checkbox. I want a formula that looks at the first checkbox and looks at the status. If status is Complete, that summary field would then indicate that the Project is in Definition. If the status is In Progress…