There is an Task hierarchy created with the layer of 5 Main sub task.
For this 5 layer Sub task Duration calculation is wrong when i tried with dependency and without dependency
Can any one help me on this
Hi Sara,
It looks and probably is correct. Check your Project Settings > Working Days so that is set up the way that you want.
The Start Date for a Parent will be automatically set to the earliest Start Date from all of its Child Rows. Similarly the End Date will be set to the last End Date from all its Child Rows.
The Duration on the Parent reflects the number of working days between the Start Date and End Date in that row. It provides the full time span encompassed by that section of tasks, from the earliest sub-task to the latest, as opposed to a sum of their durations.
The % Complete on the Parent row will calculate a weighted percentage based on both the Duration and % Complete entered on each child row. In this way, completing child rows with shorter durations won’t affect the Parent row % Complete as much as completing a longer duration child row. Because of the way this is calculated, only sub-tasks with a given Duration and a given % Complete value will be included in the parent row roll-up.
More info: https://help.smartsheet.com/articles/765753-parent-rollup-functionality
I hope this helps you!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I was archiving critical accounting data from one sheet to another by moving the rows. This is something I've done countless times in the past decade of using Smartsheet. This time, after moving nearly 3500 rows of data, I realized none of the attachments moved with the rest of the data. I've opened a case but have had…
Hi Team Is there an update on this Community post from a year go? Issues with copying in the Windows App - Table View - Smartsheet Community I have confirmed in both Desktop and Web Applications, and on multiple browsers where the Clipboard setting in "ALLOWED", but the copy/paste CTRL-C/CTRL-V is not working. It doesn't…
I have a user that has accepted their invite. They do not show up in the roles section for me to assign the user roles.