Hi,
Trying to use the =dateonly to get the variance between planned start and actual start, but it looks like the calculation is counting the weekend days when in only want it to count weekdays. Is this possible?
The networkday function should help with this use case. You can read more about this and our other functions here.
I think that is working, thanks so much!
Hi there, I have just recently worked with Smartsheet's Implementation team to build a Control Center Blueprint. The workspace that holds the solution is titled something very generic and I would like to rename it. Can I do that w/out breaking anything or what steps would I need to take to successfully rename it. Thanks in…
Hey, I've got a sheet, which is autopopulated as a source sheet to feed into DataMesh (which runs once every 24 hours). Once DataMesh has run, how can I auto-clear the rows in the sheet to avoid repeating this the next day? I have no use to keep the data and want to avoid clogging up the source sheet. I have tried…
Hello everyone seeking for an answer and help please im having a hard time on approval request automation . My workflow runs smoothly however when the approver open the attachment on the request it automatically downloads and when clicking the approve it says link are already used and auto decline teh approval request…