Hi!
I have 7 columns that have check boxes. When all 7 columns in one row are all checked, I would like a column that will auto populate a "completed" date. Is this even possible or am I insane? haha! Thank you!
This is not currently possible without a third-party solution like Zapier. There is no date-stamp option in Smartsheet although it is a HIGHLY requested item. I recommend that you submit a product enhancement request to add your vote to their list.
There is a possibility of adding a Modification date system column to your sheet, but anytime something changes on the row the modification date would change too.
Hi,
It's possible, but you would need to use a third-party tool like Zapier or similar.
Would that work?
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I'm looking for a way to attach notes to a sheet that isn't attached to a specific row. Rows for many of my sheets are cleared out in preparation for the next iteration of the project, and I need a notes/comments field that remains with the sheet even when the rows do not.
I have a workspace that I am looking to move items from into a new workspace. The reason I want to do this is becasue there are individuals that have access to the original workspace that do not need access to everything that is currently in the workspace. In the original workspace is a MAIN document that holds all…
How to use Smartsheet AI/automation to automically write project status?