I don't see an option for it in the "View" button for my project. I did find this article in the help pages:
https://www.smartsheet.com/pert-101-charts-analysis-and-templates-more-accurate-project-time-estimates#pert-analysis-how-likely-will-the-project-be-on-time
Which says "if you do it by hand" implying there's another option.
Please advise.
Hello—
Smartsheet has Gantt chart functionality, and as such, has critical path functionality: https://help.smartsheet.com/articles/1979152-tracking-a-project-s-critical-path
I understand that this is similar, but not the same as PERT. Currently, Smartsheet doesn't have functionality to build a PERT chart. When you have a moment, please submit an enhancement request using the form under Quick links to the right of the community site to let our Product team know that you'd like to see this capability added.
I was wondering if this was actually happening or if something weird was going on with my automation. But, after 3 days, my approval requests will auto-deny and wreck my workflow, marking things as denied, even when I haven't gotten to them yet. I have a formula and a helper column that documents when an approval has gone…
Does anyone know if there is a way to produce a similar graph to the attached image? I have the data in SmartSheet but can't figure out how to do the graph with both the background tiers and the performance line.
Hello! Does Lastest Comment still exist? I'm not able to assign this property to a field. I used it a few years ago and now it is grayed out.