Is it possible to block out certain dates with a date field in a form? For example, when the calendar comes up for March 2019, I don't want March 15 as an option. Is this possible?
Hi Julie,
Unfortunately, it's not possible at the moment, but it's a great idea!
Please submit an Enhancement Request when you have a moment.
It could be possible with an add-on or third-party solution.
Would that be an option?
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Hello,
As a potential work around, you could consider creating an update request rule to be sent when the date column changes to a specific date.
For example, when March 15th (or any other date that you specify) is entered, an update request will be sent to the form submitter, promoting them to choose another date.
Here's an example of what the update request rule could look like:
If your goal is to prevent duplications, you could insert a flag or checkbox column and then enter a formula that will flag or check the column if a date has been entered more than once. The formula would look something like this:
=IF(LEN(Date@row) = 0, "", IF(COUNTIFS(Date:Date, Date1) = 1, 0, 1))
You can then send an update request to the submitter when the flag or checkbox column has been flagged or checked. Here is what the update request would look like:
If you choose to implement this workaround, you'll want to keep the following in mind:
You might also want to consider publishing a report with the taken dates so that submitters can see what isn't available. A link to the published report can be inserted into the form by inserting the link in a Header/Description field.
If needed, more information on this can be found in our help articles:
Hi All, When I go to Account - Personal Colours and Logo and update my logo from the standard smartsheet logo to a company logo, it doesn't save. I have tried uploading the logo both on my personal smartsheet account and the account holder's smartsheet account. I would love some help if anyone has some idea of how to make…
Hi team, Target sheet isnt updating as per the source sheet, need to discuss and close this issue ASAP i am willing to connect right away
Please help! I've tried Smartassist with no luck! I'm creating a project financial tracking template and have hit a challenge with charting. My source sheet contains one row per month and includes: Financial Month (stored as text) Actuals (Cumulative) Forecast (Cumulative) A helper column called "In Plan" that I use for…