I can't figured out why #INVALID DATA TYPE auto fill when I haven't pick a date for the start and finish date. If I do have those fill out then the formula works fine but otherwise it just fill the duration cell with that error. I do have the duration column under Text/Number. The only thing that I can think about is that I have multiple reports that generate from this Master Sheet but other than that I don't see where is the mistake.
Try wrapping your formula with an IFERROR formula. Use "" to return a blank.
=IFERROR(NETDAYS([Concept Start Date]@row,[Concept Finish Date]@row),"")
Thanks!!!
It worked! I ended up using the formula
=IFERROR(NETDAYS([Concept Start Date]10, [Concept Finish Date]10), "")
it actually delete the #INVALID DATA TYPE
Using @row instead of the row number just makes it easier to copy formulas. You may run into a situation where you copy the formula, to say row 700, and the formula still shows row 10 (using the data on row 10, instead of row 700).
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…