Is there a way to set up an alert on a sheet for when it is nearing the 5000-row limit?
Thanks!
You would need to use a helper column to establish how many rows are currently on a sheet. You could then set up a notification to trigger when the number in that column reaches a certain amount.
Hi Lisi,
To add to Paul's suggestion.
The helper column could be an auto number column if you're not using one for anything else.
Hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Andree,
I thought about the auto-number column, but then there's the hassle of having to reset it if you happen to delete any rows.
Yes, of course! If that's the case!
Then it would be better to use a formula that would count only the actual rows.
I typically will reference a column that will always have text in it (task name for instance) and then use a straightforward COUNTIFS.
=COUNTIFS([Task Name]$1:[Task Name]@row, ISTEXT(@cell))
.
Of course you could always just reference the entire column and tuck the formula elsewhere and then trigger the notification off of that cell, but I use row numbers as a visual reference.
My particular uses involve actually displaying specific row numbers in some metrics (I believe it piggy-backs off of a solution you provided for something else) to give people the ability to quickly jump to past due tasks.
You're thinking of my TOC solution.
The SSFeatures browser extension alerts you automatically when any sheet approaches its limits - rows, columns, cells, or cross-sheet references.
By default it triggers at 80%, but you can customize the threshold.
No helper columns or formulas needed.
You can read more about this feature, and watch a demo video here:
Hope this helps!
Disclosure: I'm the creator of SSFeatures.
I've created a dashboard with multiple graphs using data from the same report. I have added the report to the dashboard as well and set up the filter for use in the dashboard. Is this filter transferable to the graphs as well, given i can filter the report in the dashboard?
Dear Community, Can you please advise? I have a sheet where among other columns I have a column listing contacts "Champions" (multiple per cell) the other columns are for example: Countries (a list of 72) The list of Projects (approx 15) - I can add to that sheet, or I can create in a Helper Sheet. I haven't done that yet…
Looking for assistance again, I want to bring in the % complete from the Production sheet to the Schedule sheet, but once the % complete is 100 the data is moved to another sheet, so I would like to reference to check 1 sheet for percent complete and if it is not there check the second sheet. Schedule sheet: Pick Up Date…