I've done some research, so I'm pretty sure I already know the answer. I have a project with a hard completion date. I would like to have any subtask scheduled backward from the completion date. Can that be done in Smartsheet?
Hi,
There is a Template called: Project with Hard Deadline and Gantt that probably is what you´re looking for.
Hope that helps!
Did it work?
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Andree,
Please enter the link for this Template or information you found. Your comments are useless to everyone searching. This is not the best website for searching and finding correct answers at the top of the list. On these community boards we need to be accurate in the links to point people in the right direction. Thanks.
At the time of my post, I don't think it was possible to link to the templates but now it is so here you go:
https://app.smartsheet.com/b/home?sc=mjjH3-k10qQ%2Cm9FH33U15fo%2C1
I hope that helps!
Workflow Consultant / CEO @ WORK BOLD
This Template is located in the SOLUTION CENTER
Go To Solution Center
Enter Search : Project with Hard Deadline
You will see the Single Project Template Called
"Project with Hard Deadline and Gantt"
Click on it and it will appear in your SmartSheet Collection
Not much to look at but at least it can start a person in the right direction for entering a Deadline Date and the remainder of items get scheduled using predecessors with SF with task below.
My link above is the direct link to open a copy in your account.
Here's a link to the Solution Center page with that specific template.
https://www.smartsheet.com/marketplace/templates/project-hard-deadline-and-gantt
I have two automations set up on a sheet, both triggered by changing the contents of a cell (same cell for both). One automation MOVES the row to another SS (basically a cemetery for dead requests). The other sends an email to a specific person to let him know that the request was denied. This Email automation was added…
Hello, I´m working on a project plan and I have a doubt if the way I write the predecessors impacts the targeted activity (dates and critical path are my main concern). Example: let's say row 50 needs rows 10, 15, 27, 33, 41 as predecessors, is there any difference if I write them in descendant, ascendant, or random order??
Hi Smartsheet Community, We're seeing an issue with Dynamic View and wanted to find out whether anyone else has experienced something similar. Scenario We have a workflow where users submit records through forms and then access the records through Dynamic View. Issue The records are successfully created, but some users…