Hi There,
Apologies if this has been addressed elsewhere, I could not find anything similar.
Are you able to status update a programme so to update % complete and the resequence the programme task to start after the today line?
Hi,
Not sure I follow!
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help.
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
With a construction programme as you progress through time you update an activity based on progress achieved. i.e. % complete. If you have an activity/task that was due for completion yesterday, but the activity progress is only at 80% complete, then this means the remainder of that activity needs to be rescheduled to start after today.
Most construction planning and programming software has the ability to "schedule" or "update" the programme where uncompleted activities are moved to the right i.e. to start after the schedule date.
Refer attached snapshot where I have tried to demonstrate what i mean.
Is there an answer to this?
Hi, We have a paid membership and we all have the field "Generate Document" except one colleague. I have made sure she is an admin but this option still does not exist when she selects the 3 dots in a row. Please can I get assistance
What are the permission and/or licencing requirements for a user to be able to export a report to excel
Two questions here, hoping someone know the answer to both. In the new browse view, if I am in a sub folder of a folder that has multiple files in it, how do you create a new folder? There is not create folder option I can find. i.e. Folder 1\folder 2 (here I have 10 files that I would like to create a folder 3, then move…