Greetings,
I have two rows with multiple date type columns.
I need to added a conditional formatting where, if the date in row is greater than the date in other row, the cell with greater date needs to be highlighted.
Someone Kindly help.
Thank you
Hi,
Unfortunately, it's not possible at the moment to accomplish it without a helper column, but it's a great idea!
Please submit an Enhancement Request when you have a moment.
Can you maybe share some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help.
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Its actually quite simple. There are two tasks, Task A and Task B. Theoretically, Task B must start once Task A is finished. But sometimes Task B starts even before Task A starts. Also, Task A is a milestone i.e., it takes place only for one day.
I just need to conditionally format the start date cell of Task B (say highlight it) if it starts before Task A.
Happy to help!
You'd have to add a so-called helper column with a formula to show that task B starts before task A.
Would that work?
Could you please elaborate. It would be helpful.
Try something like this.
=IF(ISBLANK(B@row); ""; IF(A@row > B@row; "True"))
The same version but with the below changes for your and others convenience.
=IF(ISBLANK(B@row), "", IF(A@row > B@row, "True"))
Depending on your country you’ll need to exchange the comma to a period and the semi-colon to a comma.
Did it work and make sense?
Hope that helps!
The solution you have provided works. But I have more than 400 rows in each sheet. And the tasks are not equally spaced. So, is it possible to write an equation such that, if it encounters a blank cell in the previous cell, it has to move to another cell. and keep moving until it encounters a non empty cell.
Excellent!
How would you want to use the check for an empty cell and why? What's the use case?
Hi there, I have just recently worked with Smartsheet's Implementation team to build a Control Center Blueprint. The workspace that holds the solution is titled something very generic and I would like to rename it. Can I do that w/out breaking anything or what steps would I need to take to successfully rename it. Thanks in…
Hey, I've got a sheet, which is autopopulated as a source sheet to feed into DataMesh (which runs once every 24 hours). Once DataMesh has run, how can I auto-clear the rows in the sheet to avoid repeating this the next day? I have no use to keep the data and want to avoid clogging up the source sheet. I have tried…
Hello everyone seeking for an answer and help please im having a hard time on approval request automation . My workflow runs smoothly however when the approver open the attachment on the request it automatically downloads and when clicking the approve it says link are already used and auto decline teh approval request…