Connect with peers, share your expertise, and inspire what’s next in Smartsheet — from proven practices to practical how-to insights from fellow users and product experts.
Sign in to join the conversation:
We have created a sheet which has a start date and a due date.
I would like to have the status column change to overdue once the due date is past the current date.
If someone would be able to help me that would be greatly appreciated.
Thank you
Dave
Hi Penny,
Try something like this.
=IF([Due Date]@row < TODAY(); "Overdue")
The same version but with the below changes for your and others convenience.
=IF([Due Date]@row < TODAY(), "Overdue")
Depending on your country you’ll need to exchange the comma to a period and the semi-colon to a comma.
Did it work?
Hope that helps!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
I am currently setting up an automation for people to get notified through their email, when they are prompted. But is there a way that they can reply in the email of a comment that will then go to the specific sheet. This way they do not have access to the sheet, but can just comment through email with updates?
Is there a way to revert to the old dashboard look and feel. The new dashboards do not look good at all. There is no way of knowing if there are additional items in the widgets until you scroll over one to learn there is more to it since the vertical bar doesn't show. We have hundreds of dashboards and they will all need…
When i try to send or print the timeline view instead of showing the progression bars like they do on the screen it only send the data entered and not a graph type view to print. Is there a way to do this. I am using a mac platform if that helps.