I'm looking to collect ongoing data/statistics on how many tasks reach past due. I would like to collect this by person assigned and across all projects and then by month.
Any suggestions on how to tackle this using smartsheet?
I created a spreadsheet and used a couple cross-sheet references in a Countifs formula that will count all past due tasks, and where assigned to a particular person. We then linked that data into a dashboard! Because contact columns are finicky we used an email address and a Full name field to check against the contact column. See screenshot below.
Thank you Mike, I can give that a try! I currently have a report that shows me past due tasks across all my spreadsheets but it changes based on the task getting marked as complete. Ideally, I would be able to create a stats report-- something that could show, for instance, tasks assigned to "John" become past due 25% of the time.
Ah. I see what you mean. That would require tracking the actual completion date and measuring it against the due date. You might want to add a hidden column or a flag that adds text if the assignment or is triggered when the actual completion is past the due date. Then you could divide all the past due assignments that are completed and divide them by the total completed assignments to get a percentage number.
Would that work for you?
I'm looking for a way to attach notes to a sheet that isn't attached to a specific row. Rows for many of my sheets are cleared out in preparation for the next iteration of the project, and I need a notes/comments field that remains with the sheet even when the rows do not.
I have a workspace that I am looking to move items from into a new workspace. The reason I want to do this is becasue there are individuals that have access to the original workspace that do not need access to everything that is currently in the workspace. In the original workspace is a MAIN document that holds all…
How to use Smartsheet AI/automation to automically write project status?